2007 Bond

Oak Meadows Elementary School
Architect: Fromberg Associates
CM @ Risk: Baird/Williams Construction

  • Structural steel, roofing and framing of the walls continues in the kitchen and library areas.
  • Plumbing and electrical rough-in is underway in the kitchen area.
  • Interior mechanical, electrical and plumbing is on-going in the PreK/K and 1st grade wings.
  • In the administration and gymnasium area structural steel erection is in progress.

Pictures

Decker Middle School
Architect: BLGY
CM @ Risk: Baird/Williams Construction

  • Installation of the structural steel and metal decking for the classroom wings is in progress.
  • The slab for the second story of the classroom wing should be in place by 1-28-08, weather permitting.
  • Roofing of the cafeteria and kitchen areas is on-going.  Framing of the interior walls and MEP rough-in is in progress in these areas as well.
  • Over the past month good progress has been made although several days of wet and cold weather has impacted several trades.

Pictures

2009 Elementary School - 13 Acre "Samsung" Site
Architect: Fields & Associates
CM @ Risk: Baird/Williams Construction

  • The application for the site development permit was filed with the City of Austin January 12th.
  • 100% construction documents are due to be complete in late February.  After a short review period and any necessary revision of the bid documents is completed BWC will put the project out for bid and potentially the GMP will be presented for Board approval at the April 21st Board meeting.

Admin & New Tech Phase II
Architect: O'Connell Robertson
CM @ Risk: Baird/Williams Construction

  • O’Connell Robertson is set to issue the 100% construction documents for New Tech Phase II at the end of month.  After a short review period and any necessary revision of the bid documents is completed BWC will put the project out for bid and potentially the GMP will be presented for Board approval at the March 17th Board meeting.
  • O’Connell Robertson continues to refine the schematic design for the Administration renovations.
  • Once the schematic design has been finalized the asbestos abatement package will be developed and put out for bid.
Manor ISD

Owners Building Resource, LP.