2006 Bond
Bluebonnet Trail Elementary School
Architect: BLGY
CM @ Risk: Baird/Williams Construction
- Finish out of the new gymnasium and conversion of the old gymnasium into cafeteria space is complete.
- Landscaping, site clean up and completion of punch list items is in progress.
Pictures
MISD Athletics Additions
Architect: O'Connell Robertson
CM @ Risk: Baird/Williams Construction
- The topographical survey is complete and the geotechnical investigation is nearing completion.
- OBR continues to converse with Aqua Water Supply Corporation concerning the water storage tank and agreements for such that must approved by both their Board and the MISD School Board
Manor High School Additions Phase 4
Architect: BLGY
CM @ Risk: Baird/Williams Construction
- Underground utilities site grading are on-going for the baseball field and track.
- The second story slab for the two story classroom wing is in place.
- Mechanical, electrical and plumbing rough-in is underway for the two story wing.
- Structural steel for the band hall is currently being erected.
- Additional parking on the north, east and south sides of MHS is complete.
Pictures
|

|